In early February 2016, I received a task from the Fuqing Project Department of China Nuclear Power Engineering Company. After the Spring Festival, I arranged for the installation, commissioning and training of the valve maintenance machines and valve pressure testing platforms for the Fuqing Nuclear Power Units 1, 2 and Fuqing Units 3, 4. 


From February 14th to March 10th, 2016, except for the equipment that was temporarily not installed due to insufficient power supply, in the 8AF maintenance workshop of Fuqing Nuclear Power Plant, our service engineers Wang Miao and Yang Xiaowu successfully completed the equipment installation and commissioning as per the requirements of the client, and provided theoretical and practical operation training for the operation personnel designated by the client and the service personnel of China Nuclear Maintenance Co., Ltd. 


Through this training and on-site operation guidance, the participants have mastered the safe operation procedures and maintenance knowledge for valve inspection and testing equipment, laying a solid foundation for future nuclear power valve maintenance work.


 

20163161546554860.jpg

TS-18S Valve Pressure Detection Platform

 

20163161547516939.jpg

TS-18 Valve Pressure Testing Platform

 

20163161630395320.jpg

TS-10 Mobile Valve Pressure Detection Platform

 

20163161548481708.jpg


工程服务
More
No. 1, North Street, Yanqi Economic Development Zone, Huairou District, Beijing
info@cbe-china.com
(86-010)51662238

About Us

Service items

Research and Development Project

News Updates

Official Public Account
Telephone
E-MAIL
Contact Us:
86-010-51662238
No content
Word 500(limit 500 Character)
seo seo