CBE conducted an inspection of the manufacturing process of the lifting equipment for the new factory.

On August 10, 2016, Beijing Leiming Cyber Electromechanical Technology Co., Ltd. conducted an inspection on the production progress and quality of the lifting equipment for the "Full-Scale Test Plant of the Full-Synchronous Stretching Machine". This inspection was led by Chen Yonghong, the Quality and Safety Director of CBE, and Wang Kai, the Infrastructure Engineering Administrator, accompanied them.

The lifting equipment for the "Full-Synchronous Stretching Machine Full-Scale Test Plant" is a QD type electric double-girder bridge crane with a lifting capacity of 75 tons, which is an important equipment in the production process of the "Full-Synchronous Stretching Machine" project.

The inspectors listened to the production progress report from the lifting equipment manufacturer, verified the material specifications of the crane components, the incoming inspection reports, the production process, the inspection records of the manufacturing process, the welding process assessment reports, and the qualifications of the operators, and conducted on-site inspections.

Through this inspection, it was determined that the production progress of the crane was normal, the quality inspection points were set reasonably, all quality inspection records were true, accurate, and complete, and the qualified products could be delivered on the agreed date, ensuring the smooth progress of the "Full-Synchronous Stretching Machine" project. 


 

1590110523547989.jpg

1590110525191650.jpg

1590110526194177.jpg

工程服务
More
No. 1, North Street, Yanqi Economic Development Zone, Huairou District, Beijing
info@cbe-china.com
(86-010)51662238

About Us

Service items

Research and Development Project

News Updates

Official Public Account
Telephone
E-MAIL
Contact Us:
86-010-51662238
No content
Word 500(limit 500 Character)
seo seo